Two Queensland sites at different stages of the development sequence.
Confidentiality on landowner and counterparty detail is treated as posture, not pending. Detail is released as each structural agreement reaches execution.
SEQ-400
400 MW master plan
South East Queensland
Staged 80 / 200 / 400 MW across three contiguous developments on a single controlled parcel.
Status
Stage 1 assembled. Power, water, fibre and land in place. Stage 2 and Stage 3 envelopes diligenced against the same parcel.
Power
Powerlink and Energex engagement underway. Two connection pathways under formal assessment.
Water
Established potable and process water access. Capacity confirmed against the full master plan cooling envelope.
Fibre
7 km route to QCN Fibre under MOFN. Diverse second path via Energex pole-mounted fibre. Subsea adjacency in scope.
Land
25 hectares controlled. Expansion area assembled for Stages 2 and 3.
Second Queensland origination. Power-led screening against transmission corridors, with a structured landowner pathway.
Status
Site shortlist and grid connection screening complete.
Power
Transmission corridor identified. Connection enquiry pathway in preparation.
Disclosure
Region-only naming until structural agreement is in place. Detail released on execution.
Pipeline
Where Continode is sourcing capacity across Australia.
Brisbane, Queensland400 MW (staged)Sydney, New South Wales50 to 150 MWMelbourne, Victoria50 to 150 MWAdelaide, South Australia45 MWPerth, Western Australia50 to 150 MWHobart, Tasmania25 to 100 MW
Active corridor: Queensland. Origination underway across NSW, Victoria, South Australia and Western Australia. Detail released by region as structural agreements move into execution.