Back to projects

Project sheet — QLD-200

Queensland 200 MW site under origination.

Transmission corridor identified. Connection enquiry pathway in preparation. This site is at an earlier stage than SEQ-400 — no site control, no capital partner conversations, no tenant engagement. Disclosed at region-only until structural landowner agreement is executed.

Disclosure standard: This site is in origination. Nothing here is confirmed beyond what is explicitly stated. Items marked [VERIFY] are placeholders for Gary to confirm before external distribution of this sheet.

Current status

Where this site sits in the development sequence.

Stage
Site origination — shortlist and grid connection screening complete. Structural landowner engagement not yet commenced.
Disclosure policy
Region-only naming until a structural landowner agreement is executed. Site address, landowner identity and counterparty detail released on execution. This is operational posture, not pending paperwork.
Current work
Site shortlist narrowed. Transmission corridor identified. Connection enquiry pathway in preparation with the relevant TNSP. [VERIFY: Gary to confirm which corridor/TNSP is in scope]

Power

Transmission corridor and connection pathway.

Transmission corridor
Identified. Matches a 200 MW envelope. Connection enquiry pathway in preparation — not yet lodged. [VERIFY: Gary to confirm corridor location and TNSP]
Capacity envelope
200 MW target. Connection screening confirms the corridor can support this load profile subject to formal enquiry and augmentation studies.
Connection application timeline
Enquiry lodgement planned once site control terms are agreed with the landowner. Indicative 24–36 months to energisation from application lodge, consistent with current Australian TNSP queue conditions.
BTM assessment
Not yet scoped at this stage. Will be assessed in parallel with grid-first pathway once site control is advanced.

Site characteristics

Land, zoning, water and fibre at screening level.

Region
Queensland. Specific location withheld. Site is grid-adjacent in the identified transmission corridor.
Land area
Sufficient for a 200 MW development envelope. Indicative parcel size not disclosed until landowner engagement is formalised. [VERIFY: Gary to confirm approximate hectare range for disclosure]
Land tenure
Landowner engagement not yet commenced at the structural agreement level. Pathway identified and screened. Approach strategy in preparation.
Zoning
Preliminary assessment complete. Industrial or compatible use confirmed. No rezoning required anticipated for data centre use. [VERIFY: Gary to confirm zoning designation from screening]
Water and cooling
Water access pathway identified. Cooling feasibility assessed at screening level — not confirmed against a specific supply agreement. [VERIFY: Gary to confirm water source identified in screening]
Fibre
Carrier route logic assessed at screening level. Fibre proximity confirmed. Route survey not yet commissioned. [VERIFY: Gary to confirm carrier and route distance estimate]

Commercial structure

Origination position and stage-appropriate scope.

What Continode is offering
The same origination position as SEQ-400 — site identification, grid connection pathway, land control, water and fibre access, and capital structuring — assembled through the Continode development sequence. This site is at an earlier stage than SEQ-400.
Tenant and capital status
No tenants engaged at this site. No capital partner conversations commenced. The site must reach site control and connection application stage before investor materials are prepared.
Commercial structure
To be determined once site control is achieved. Wholesale colocation and neocloud structures both in scope depending on tenant and capital mandate at that time.
EPC delivery
Alliance partner selection deferred until site control and connection application are advanced.

Development timeline

Stage gates from here.

Current stage
Site origination. Shortlist complete. Transmission corridor identified. Landowner engagement not yet commenced.
Next gate
Landowner approach and structural agreement. Connection enquiry lodgement with TNSP. Parallel capital and tenant dialogue preparation.
Site control target
Subject to landowner engagement timeline. No commitment made at this stage. [VERIFY: Gary to confirm target timeline for landowner approach]
Energisation
Not foreseeable at this stage. Dependent on site control, connection application, and capital commitment milestones.
SEQ-400 project sheetContinode investment briefAll projects